DC Circuit Blocks DOE Order Keeping J.H. Campbell Coal Plant Open
A federal appeals court unanimously blocked a Trump administration order forcing Michigan's J.H. Campbell coal plant to stay open past its planned retirement.
By Muhamed Porić
October 3, 2026 at 2:40 AM

A federal appeals court has struck down a Trump administration order forcing Michigan's J.H. Campbell coal plant to stay open past its planned retirement, ruling unanimously that the Department of Energy exceeded its emergency powers.
The unanimous decision by a three-judge panel of the U.S. Court of Appeals for the District of Columbia Circuit marks a legal setback for executive efforts to prop up aging fossil fuel infrastructure under federal emergency statutes.
"The DOE needs to stay in its lane and use its emergency powers only in actual emergencies. Preventing the market-driven retirements of coal plants to advance a coal-friendly agenda is not a proper use of emergency powers," said Michael Lenoff, attorney at Earthjustice, according to CNBC.
Economics of the J.H. Campbell Facility
The 64-year-old J.H. Campbell coal plant located in West Olive, Michigan, was originally scheduled to shutter in May 2025 because it was no longer economic to operate in a shifting energy market.
Despite the utility's plans for retirement, the facility remained active under an emergency order issued by the Department of Energy, then led by Energy Secretary Chris Wright. Federal law contains rare emergency provisions intended to address immediate grid reliability crises, but the court found the administration stretched these authorities beyond their legal boundaries.
Financial Impact on Utility Operations
Forcing the coal-fired generator to continue burning fuel carried substantial financial consequences for utility operators and regional ratepayers.
Extended operations at the West Olive plant cost utility Consumers Energy $295 million between May 2025 and June 2026, according to data cited by the Michigan attorney general's office.
"While that happens, we are continuing to comply with the current 90-day Department of Energy order that keeps the Campbell plant operating," said Brian Wheeler, spokesperson for Consumers Energy, according to CNBC.
Legal Precedent for Emergency Powers
What is at stake in the ruling is the boundary between federal intervention and wholesale electricity market economics. The Federal Power Act allows the energy secretary to issue emergency orders to preserve grid reliability during acute energy shortages or extreme weather events.
Environmental advocates and utility watchdogs argued that using these provisions to prevent routine, scheduled plant retirements turns temporary emergency tools into permanent industrial policy. The D.C. Circuit panel's decision curtails the executive branch's ability to bypass normal regulatory channels when attempting to sustain aging coal capacity against broader economic trends.
Muhamed Porić